Delivery Plan & Timeline

Our comprehensive timeline shows how the West Hendon Broadway will be delivered in carefully planned phases from 2020 through to completion in 2026.

Project Timeline Overview

A six-year journey transforming West Hendon into a thriving, connected community.

Completed2020 - 2021

Planning & Approval Phase

Comprehensive planning applications, community consultation, and regulatory approvals secured.

  • • Planning permission granted
  • • Environmental impact assessments completed
  • • Community engagement sessions held
  • • Detailed design development
UpcomingJuly 2025

Traffic Switch

Major traffic changes including new traffic lights and road direction reversals.

  • • New traffic lights at Station Road switched on
  • • Station Road opens to two-way traffic
  • • Direction reversed on Wilberforce Road and Herbert Road
  • • Perryfield Way permanently closed to through traffic
  • • Traffic lights at Perryfield Way and Herbert Road removed
FutureJuly 2025 to Early 2026

Stage 2: Final Works

Completion of remaining Station Road work and West Hendon Broadway improvements.

  • • Complete remaining Station Road work
  • • Improvements to West Hendon Broadway between Cool Oak Lane and Garrick Road
  • • Alternating lane closures to facilitate progress
  • • Night-time carriageway resurfacing towards program end
OngoingThroughout Works

Minimizing Disruption

Comprehensive measures to reduce impact on residents and businesses during construction.

  • • Advanced warnings of significant disruptions
  • • Maintain access for residents and businesses wherever possible
  • • Phased approach ensures minimal impact on local community
  • • Temporary closures, diversions, and occasional night work as needed
Coming SoonComing Months

Next Steps

Clear communication and official announcements as the works progress.

  • • Publish Traffic Management Orders for permanent road changes
  • • Official announcement of Perryfield Way stopping up
  • • Further briefings for businesses and residents
  • • Advance notice of major traffic switch (July 2025)

Key Milestones Ahead

Important dates and developments that will shape the next phase of the project.

November 2024

Major Highway Works Start

Major highway reconfigurations begin, including road widening and upgrades to existing junctions and crossings.

Winter 2025

First Homes Groundbreaking

Construction of the first phase of new houses begins, marking a major milestone in the development.

July 2025

Perryfield Way Closure

Permanent closure of Perryfield Way to through traffic, with alternative routes fully operational.

Summer 2025

Construction of New Health Centre

Construction begins on the new Health Centre and public facilities.

May-June 2026

Highway Works Completion

The Main Highway work are planned to be complete before Summer 2026.

Stay Informed

Get the latest updates on our progress and upcoming milestones.

Current Progress

View detailed progress reports and see how construction is advancing across all phases.

View Progress

Latest News

Stay up to date with the latest developments, announcements, and community information.

Read News

Questions About the Timeline?

Our team is available to discuss any aspects of the delivery plan and how it might affect you or your business.